Capital Project Updates
-
As the capital project moves forward, check back often to receive updates and photos of the progress.
-
Progress Report: November 2021
Phase 1
Work is now complete.
Phase 2
Hannibal High School
-
Continued addressing final punchlist items.
-
K&K is working on signage replacement.
-
Continued contractor demobilization from the site.
-
Continued with contractor closeout process
HS Site & Existing Bus Garage
- Work is complete
Kenney Middle School
-
Continued addressing punchlist items.
-
Completed public address system upgrades
-
Completed balancing, awaiting colder weather to finish commissioning of new systems.
Fairley Elementary School
-
Continued addressing punchlist items.
What's Next?
Below is 30-day outlook for project work.
Phase 1
-
Work is complete
Phase 2
Continue as-builts, O&M manuals, training, attic stock turn over, and closeout process
High School
-
Complete addressing final punchlist items.
-
Complete commissioning of new systems.
-
Complete contractor demobilization from the site.
High School Site & Existing Bus Garage
- Work is complete.
Middle School
- Continue addressing punchlist items.
-
Complete commissioning of new systems.
Fairley Elementary
-
Continue addressing punchlist items.
Progress Photos
Throughout the project, photos will be posted to highlight some of the major areas of improvement. Check back often for additional photos and information.
-