Capital Project Updates

  • As the capital project moves forward, check back often to receive updates and photos of the progress.

  • Progress Report: November 2021

    Phase 1

    Work is now complete.

    Phase 2

    Hannibal High School

    • Continued addressing final punchlist items.

    • K&K is working on signage replacement.

    • Continued contractor demobilization from the site.

    • Continued with contractor closeout process

    HS Site & Existing Bus Garage

    • Work is complete

    Kenney Middle School

    • Continued addressing punchlist items.

    • Completed public address system upgrades

    • Completed balancing, awaiting colder weather to finish commissioning of new systems.

    Fairley Elementary School

    • Continued addressing punchlist items.


    What's Next?

    Below is 30-day outlook for project work.

    Phase 1

    • Work is complete

    Phase 2

    Continue as-builts, O&M manuals, training, attic stock turn over, and closeout process

    High School

    • Complete addressing final punchlist items.

    • Complete commissioning of new systems.

    • Complete contractor demobilization from the site.

    High School Site & Existing Bus Garage

    • Work is complete.

    Middle School

    • Continue addressing punchlist items.
    • Complete commissioning of new systems.

    Fairley Elementary

    • Continue addressing punchlist items.


    Progress Photos

    Throughout the project, photos will be posted to highlight some of the major areas of improvement. Check back often for additional photos and information.