Skip to main content

Updates

As the capital project moves forward, check back often to receive updates and photos of the progress.

  • Phase 1

    • Work is now complete.

     

    Phase 2

    • Hannibal High School
      • Continued addressing final punchlist items.
      • K&K is working on signage replacement.
      • Continued contractor demobilization from the site.
      • Continued with contractor closeout process
    • HS Site & Existing Bus Garage
      • Work is complete
    • Kenney Middle School
      • Continued addressing punchlist items.
      • Completed public address system upgrades
      • Completed balancing, awaiting colder weather to finish commissioning of new systems.
    • Fairley Elementary School
      • Continued addressing punchlist items.

     

    Phase 3
    Work is getting underway. The project includes renovations to the FES Music Room, Nurse's Office, and Cafeteria/Kitchen; renovations to the DMK Art Room, Cafeteria Floor, Nurse's Office; and the creation of a walking path from DMK to FES to the track.

  • Below is future outlook for project work.

    Phase 1

    • Work is complete

     

    Phase 2

    • Continue as-builts, O&M manuals, training, attic stock turn over, and closeout process
      • High School
        • Complete addressing final punchlist items.
        • Complete commissioning of new systems.
        • Complete contractor demobilization from the site.
      • High School Site & Existing Bus Garage
        • Work is complete.
        • Middle School
        • Continue addressing punchlist items.
        • Complete commissioning of new systems.
      • Fairley Elementary
        • Continue addressing punchlist items.

     

    Phase 3

    • Grounds
      • Walkways: From July 8 – August 16 (does not include topsoil/seed to grow)
    • DMK Work
      • Nurse’s Office Renovation: Fall 2024 (September 1 – March 30)
      • DMK Art Room Renovation: Fall 2024 (September 1 – March 30)
      • Cafeteria Flooring: Fall/Winter 2024/2025    
    • FES
      • Nurse’s Office Renovation: Fall 2024 (September 1 – March 30)
      • FES Music Room Renovation: Fall 2024 (September 1 – March 30)
      • Kitchen: Spring: 2025 (April 14-August 14)

Progress Photos

Throughout the project, photos will be posted to highlight some of the major areas of improvement. Check back often for additional photos and information.